Dominguez HS Temporary Kitchen


Villarruel Architects was selected to design a new temporary kitchen at Dominguez HS for the Compton Unified School District.

Dominguez HS Temporary Kitchen Dominguez HS Temporary Kitchen Dominguez HS Temporary Kitchen
Dominguez HS Temporary Kitchen Dominguez HS Temporary Kitchen Dominguez HS Temporary Kitchen
Description:

The existing campus cafeteria building caught fire and due to the substantial damage, the building was deemed a total loss by the insurance company. The school district needed to continue to serve breakfast and lunch to approximately 1700 students. Villarruel Architects was engaged to prepare plans and specifications for a temporary kitchen building. Four used modular classrooms purchased and modified to support our design for new kitchen equipment including a Type 1 hood, ranges, ovens, grease interceptor, refrigerators, sinks, serving lines and lockers. The kitchen was submitted to the Health Department concurrent with the DSA submittal to save time. Our drawings were approved by DSA in September 2024 and the project was bid constructed and completed on March 2025. The approval process required LA County Environmental Health, City Public Works and Local Fire Department approval. The project was completed at budget and in a very short time schedule.

Client:
Compton Unified School District

Date: 2025

Size: 3,840 sf ft

Cost: $1,603,959

More Educational Projects

Villarruel Architects, Inc
Architecture + Planning + Interiors